Taseko Mines Reports Second Quarter Copper Production and Operational Update for Gibraltar Mine
Metal production in the second quarter was impacted by mill downtime for the relocation of the in-pit crusher and concurrent maintenance activities in concentrator #1, as well as a strike by the mine's unionized workforce in June. The in-pit crusher move was completed in late May but the final installation work and the other mill maintenance was interrupted by the 18-day strike in June. This work resumed following the strike, when contractors were able to return to site, and is now completed. Concentrator # ...