IREN increases Childress power capacity from 600MW to 750MW
IRENIris Energy (IREN) Newsfilter·2024-07-24 11:23

The Company is pleased to announce it has secured an additional 150MW of immediately available power capacity at its Childress site. This increase follows the approval of network studies by ERCOT and execution of an amended connection agreement with AEP. 2024: 910MW immediately available power 510MW of data centers planned in 2024 (30 EH/s) 910MW of data centers planned in 2025 2026: 1,400MW West Texas site on schedule Data center planning underway 2027-2030: >1GW of additional development pipeline IREN is ...