Dominion Energy Successfully Completes First Monopile Installation Season for On-Time and On-Budget Coastal Virginia Offshore Wind
DDominion Energy(D) Prnewswire·2024-11-01 15:00

Exceeded initial objectives with 78 monopile foundations and 4 offshore substation foundations safely installed since May 22 Second installation season begins May 2025 CVOW is fully permitted by state and federal authorities, remains on-budget and on schedule to complete construction in late 2026RICHMOND, Va., Nov. 1, 2024 /PRNewswire/ -- Dominion Energy announced today that 78 monopile foundations and 4 offshore substation foundations were installed for the 2.6-gigawatt Coastal Virginia Offshore Wind (CVO ...