Greater Houston Resiliency Initiative Phase Two Monthly Update: CenterPoint Energy continues to make good progress with more than 7,000 stronger poles installed across the area in less than 100 days
Actions throughout GHRI Phase Two include installation of stronger poles, clearance of more vegetation miles, undergrounding of more power lines and additional "self-healing" devices When complete, GHRI Phase Two actions will improve reliability by saving customers more than 125 million fewer outage minutes annually. HOUSTON, Dec. 12, 2024 /PRNewswire/ -- Today, as part of the second phase of its Greater Houston Resiliency Initiative (GHRI), CenterPoint Energy shared it latest monthly progress update with n ...