Workflow
皖能电力:公司2025年发电量预计将继续保持增长
000543WENERGY CO.,LTD.(000543) 证券时报网·2025-01-24 04:27

Core Viewpoint - The company expects its power generation capacity to continue growing by 2025, driven by new production capacity coming online [1] Group 1: Company Performance - The company's coal-fired power units have achieved full profitability [1] - The total capacity of the company's coal-fired power units is 13.17 million kilowatts, including units under construction [1] Group 2: Future Projects - A major coal-fired power unit at the Yanjinzi Phase II is expected to be operational in the first half of this year [1] - Three coal-fired power projects, namely Guoan Phase II, Anqing Phase III, and Zhongmei Liu'an, are expected to be completed by 2026 [1] - The Chizhou Phase II project is anticipated to be operational by mid-2025 [1]