Core Insights - i-80 Gold Corp has finalized two third-party processing agreements for toll milling and ore sales, effective until December 31, 2027, which are crucial for advancing the development of its underground gold mines [1][3] - The refurbishment of the Lone Tree autoclave facility is targeted for completion by December 31, 2027, allowing for processing of all material from the company's underground gold mines [1][6] - A class III engineering study on the autoclave refurbishment is expected to be completed by the end of Q3 2025 [4] Company Overview - i-80 Gold Corp is focused on becoming a mid-tier gold producer in Nevada, holding the fourth largest gold mineral resource in the state, with a portfolio of high-grade development and production-stage projects [5] - The company is executing a hub-and-spoke regional mining and processing strategy to maximize efficiency and growth, leveraging its fully permitted central processing facility [5]