Silvercorp Announces the Construction Plan and Schedule for the Development of the El Domo Project

Capital Cost Estimate Details The table below summarizes the schedule and costs to construct the El Domo Project: | | | Fiscal 2026Fiscal 2027Total | | | --- | --- | --- | --- | | | ($ Million) | ($ Million) | ($ Million) | | 1Package #1 - Site preparation/Roads/Channels/TSF/SWD | $29.2 | $18.2 | $47.5 | | 2Package #2 - Open Pit Mining and Stripping | 7.0 | 32.0 | 39.0 | | 3Package #3 - Processing Plant Construction and Equipment | 14.0 | 19.0 | 33.0 | | 4Temporary and Permanent Camps | 2.0 | 5.0 | 7.0 | | ...