Port Access Approval Received as Last Key Item for FID at Minim Martap Bauxite Project
Globenewswire·2025-04-30 05:28

Highlights: With port access approval in place, detailed design for bauxite port loading infrastructure has now commencedFinal tenders received for mine development and road access upgrade to Inland Rail Facility (IRF) Engineering design of IRF approximately 50% completedEvaluation of rail and port capacity upgrade from 6Mtpa to 10Mtpa now underwayPort access approval is the final condition precedent for EEA to exercise its 500 million options (approximately $US22M)First locomotive delivery scheduled for Q1 ...