Montage Gold Reports on Its Q1-2025 Activities
Globenewswire·2025-05-27 10:30
Koné project construction on-budget and on-schedule • Strong continued exploration focus • Robust liquidity sourcesCONSTRUCTION ACTIVITIES Over 2.0 million hours worked without a Lost Time Injury, with more than 2,100 employees and contractors on-siteWell on track for first gold pour in Q2-2027 and on budget with over $304 million of capital committed as at today, representing approximately 36% of the total capital expenditure, with prices in line with expectationsCIL ring beams were completed two months ah ...