农心科技:技改项目达到预定可使用状态时间延期至2026年3月31日
NORSYNNORSYN(SZ:001231) news flash·2025-06-26 11:15

Core Viewpoint - The company has adjusted the expected operational status date for its "Green Pesticide Formulation Intelligent Digital Factory Technology Renovation Project" from June 30, 2025, to March 31, 2026, due to project progress and equipment trial runs [1] Summary by Relevant Sections - Project Timeline Adjustment - The board and supervisory board approved the adjustment of the project's expected operational status date [1] - The new expected operational status date is now set for March 31, 2026 [1] - Investment Progress - As of June 21, 2025, the project has accumulated an investment of 33.0486 million yuan, representing a progress rate of 77.42% [1] - Impact on Operations - The adjustment will not adversely affect the company's operations and is in compliance with relevant regulations [1]