政府投资13亿元建设公用项目——抚顺高新区50余家企业将用上低价汽
Liao Ning Ri Bao·2025-06-27 01:07

Group 1 - The construction of the cogeneration project in Fushun High-tech Zone is progressing rapidly, with the main plant's earthwork halfway completed and temporary pipelines laid [1] - Upon completion, the project will generate 568 tons of steam per hour and an annual electricity output of 27.4 million kilowatt-hours, meeting the steam needs of over 60 enterprises [1] - The project has a total investment of 1.374 billion yuan and is expected to be completed by December 2026, aiming to provide low-cost steam to local enterprises [1] Group 2 - Fushun Qilong Chemical Co., a leading company in the domestic petroleum resin industry, estimates that it will save over 10 million yuan annually in production costs due to the new steam supply [2] - The government initiative to lower production costs is enhancing the confidence of enterprises in investing and developing in the Fushun High-tech Zone [2]