Core Viewpoint - The company announced a delay in the completion of its "Intelligent Automation Equipment Production Base Construction Project" from the original deadline of November 30, 2024, to November 30, 2025, due to various factors affecting the construction schedule [1] Group 1 - The project was initially scheduled to be operational by November 30, 2024 [1] - Delays were caused by heavy rainfall, power grid approval processes, fire safety, civil defense, and quality inspection issues [1] - The company has decided to extend the project timeline to ensure construction quality [1] Group 2 - The delay will not change the project's content or the implementing entity [1] - The project delay is not expected to adversely affect the company's normal operations [1]
春光智能:智能自动化装备生产基地建设项目延期至2025年11月30日
news flash·2025-06-27 11:57