长源电力:谷城县盛康镇50MW农光互补光伏发电项目动态总投资调整为2.16亿元

Core Viewpoint - The company has adjusted the planned installed capacity and total investment for its photovoltaic power generation project in Gucheng County, indicating a strategic shift in project execution [1] Group 1: Project Details - The planned installed capacity of the Gucheng County photovoltaic project has been revised from 50 MW to 47.9 MW [1] - The total investment for the project has been reduced from 259 million yuan to 216 million yuan [1] - As of May 31, 2025, the actual usable land area for the photovoltaic project is 1,387 acres, with 19 power generation units completed [1]