新疆环塔里木盆地750千伏输变电工程全线贯通
news flash·2025-07-13 05:24

Core Points - The Tarim Basin 750 kV power transmission and transformation project has been fully completed after 15 years of construction, creating a 750 kV ultra-high voltage transmission ring network around the Tarim Basin [1] - The project consists of 9 phases of 750 kV power transmission and transformation works, including 9 substations, nearly 10,000 transmission towers, and a total line length of 4,197 kilometers [1] - Out of the 9 segmented projects, 8 have already been put into operation, with the final segment expected to be operational by November this year after acceptance and defect rectification [1]