Bear Creek Mining Announces Q2 2025 Mercedes Production Results and Drawdown of Funds
Newsfileยท2025-07-16 12:00

As in the first quarter of the year, delayed production from Marianas was partially offset by accelerating pillar removal at San Martin, which deposit has now been fully mined. While gold grades and gold recovery improved quarter over quarter, the slow pace of mine development activity at Marianas, in combination with protractions in work on a new ventilation shaft resulting from poor rock conditions, led to a shortage of available production faces and negatively impacted development meters and both mined a ...