鄂尔多斯市东胜区油房壕煤矿建设顺利推进

Group 1 - The oilfanghao coal mine project in Dongsheng District is progressing with construction activities such as shaft and roadway construction, and equipment operation [1] - A "daily assessment and weekly promotion" mechanism has been established to enhance project efficiency, with strict quality control measures in place [1] - The project aims for an annual production capacity of 5 million tons, with expected revenue of 1.9 billion yuan and tax revenue of 250 million yuan upon completion in the first half of 2027 [9] Group 2 - The civil engineering works are advancing steadily, with the completion of various facilities including the employee cafeteria and the administrative office building [4] - The installation engineering has seen the completion of 743 pile foundations for the raw coal, product, and gangue warehouses [4] - The project is on track to meet its annual construction goals, with ongoing coordination of various construction phases [6]