Workflow
今年前三季香港中电数据中心售电量按年升6.7%
Zhong Guo Xin Wen Wang·2025-10-20 12:25

Group 1 - The core point of the article is that Hong Kong's CLP Power reported a 6.7% year-on-year increase in electricity sales to data centers, despite an overall decrease of 1.8% in total electricity sales for the first nine months of 2025 due to lower average temperatures [1][3] - The company has identified approximately 8,000 suitable locations for the construction of fast charging stations to meet the growing demand from the Hong Kong government and the industry [3] - CLP Power is implementing measures such as grid reinforcement, additional system maintenance, and power quality testing, while utilizing zero-carbon electricity to ensure optimal power supply for major sporting events [3] Group 2 - The clean energy transmission system connecting Hong Kong and mainland China is on track to complete a large-scale capacity expansion project by early 2026, which will allow for the input of more zero-carbon energy to support Hong Kong's decarbonization efforts [3]