Core Viewpoint - The Inner Mongolia Autonomous Region's Industrial and Information Technology Department has announced a notification regarding the implementation of normalized staggered production for cement from 2025 to 2026, mandating all cement clinker production lines in the region to participate in staggered production [1] Group 1: Staggered Production Implementation - The staggered production period will be from November 1, 2025, to March 31, 2026, lasting for a total of 5 months [1] - The staggered shutdown of kilns will be defined as a cycle from the start date at midnight to the end date at 24:00, including the time for kiln heating [1] - The regional cement association is tasked with organizing staggered production during the summer and autumn seasons based on air quality, market supply and demand, and regional differences [1]
内蒙古自治区工业和信息化厅:11月1日起5个月水泥熟料生产线实行错峰生产
Xin Hua Cai Jing·2025-10-22 04:48