金石资源:蒙古国选矿厂的带料生产调试以及取水工程、尾矿库建设预计将在2026年4月后继续进行

Core Viewpoint - The company has nearly completed the construction and installation of its mining plant in Mongolia, with plans to conduct single machine debugging soon, but full production will be delayed until after April 2026 due to harsh winter conditions [1] Group 1: Project Status - The mining plant project in Mongolia is expected to start single machine debugging shortly [1] - Construction and installation of the plant have been largely completed [1] - Full production and related construction activities are anticipated to resume in April 2026 due to winter weather constraints [1] Group 2: Production and Sales - From January to September this year, the mining project has produced approximately 85,000 tons of fluorite ore with a grade of about 40% after pre-treatment [1] - Of the produced ore, 41,000 tons have been transported to domestic facilities for processing or sale [1]