蒙古能源(00276):于胡硕图煤矿的新海关监管堆场建造抑尘墙
智通财经网·2025-11-28 09:30

Core Viewpoint - Mongolia Energy (00276) announced a contract for the construction of a dust suppression wall at the Khushuut coal mine, with a total cost of 2.689 billion Mongolian Tugrik (approximately 5.863 million HKD) [1] Group 1: Contract Details - MoEnCo signed a contract with a contractor for the dust suppression wall on July 22, 2025 [1] - The construction progress was delayed due to the trial operation of the smart washing plant [1] - To ensure completion of the dust suppression wall by early next year, MoEnCo and the contractor signed a change order on November 28, 2025, allowing winter construction at an additional cost of 784 million Mongolian Tugrik (approximately 1.7093 million HKD) [1] Group 2: Total Project Cost - The total cost of the construction project, including the change order, amounts to 3.44 billion Mongolian Tugrik (approximately 7.5724 million HKD) [1]