云南锗业:公司于2025年3月开始实施“空间太阳能电池用锗晶片建设项目”
Core Viewpoint - Yunnan Germanium announced the implementation of a new project for space solar cell germanium wafers, set to begin in March 2025, with a total production capacity of 2.5 million wafers upon completion [1] Group 1: Project Details - The project will have a construction period of 18 months, aiming to achieve an annual production capacity of 1.25 million germanium wafers by the end of 2025 [1] - The new capacity will be built on top of the existing production capabilities, ensuring that current production lines remain unaffected during the project [1] - The construction work for the project is currently progressing as planned [1]