Core Viewpoint - The company has begun to meet customer delivery demands since August, driven by the release of capacity at the Shunde Phase II base and improvements in the 2.0 technology [1] Group 1: Production Capacity and Expansion - The new base's production is primarily aimed at matching the incremental demand from customers during the 14th Five-Year Plan period [1] - The company has accelerated preparations for the Zhuzhou base, with 90% of infrastructure completed, 60% of electromechanical installations done, and 70% of the first batch of production equipment being debugged [1] - The selection process for personnel at the Zhuzhou base has been completed, and skills training is being strengthened [1] Group 2: Future Projections - The Zhuzhou base is expected to commence production by mid-January next year [1]