Orezone Reports First Gold from Bomboré Hard Rock Expansion
Globenewswire·2025-12-15 23:06

Core Viewpoint - Orezone Gold Corporation has successfully completed its first gold pour from the new 2.5Mtpa hard rock expansion, marking a significant milestone in its operations [1][3]. Group 1: Operational Achievements - The commissioning of the new plant is complete, with mill throughput averaging 78% of nameplate capacity during the first five days of operations [1]. - The construction and commissioning of the Bomboré hard rock expansion were completed on time and on budget within approximately 12 months [2]. Group 2: Future Production Expectations - Commercial production is anticipated to be declared in early Q1-2026, which will represent a major milestone for the company [3]. - Overall gold production at Bomboré is projected to increase by 45% to between 170,000 and 185,000 ounces in 2026 [3][4]. - The company is advancing stage 2 of the hard rock expansion, which is expected to further increase annual production to between 220,000 and 250,000 ounces [4].