Core Viewpoint - The company has made significant investments in wastewater treatment projects, with ongoing developments and extensions in project timelines [1] Investment Projects Summary - The Fuzhou Lianshan Wastewater Treatment Plant Phase III project has accumulated an investment of 238 million yuan and has commenced commercial operations [1] - The Fuzhou Binhai New City Airport Wastewater Treatment Plant PPP project has seen an investment of 119 million yuan, which has completed water testing and is now in trial operation [1] - The company has invested 42.77 million yuan to supplement working capital [1] Project Timeline Adjustments - On July 19, 2024, the company's board approved a delay in the water testing schedule for the Fuzhou Binhai New City Airport Wastewater Treatment Plant PPP project [1] - On August 1, 2025, the board further agreed to extend the water testing timeline to the end of December 2025 [1]