丰州220千伏输变电工程投运
Xin Lang Cai Jing·2025-12-21 09:22

Group 1 - The core point of the article is the successful commissioning of the Fengzhou 220 kV transmission and transformation project, which enhances the power grid structure in Hohhot, Inner Mongolia, and supports high-quality development in the region [1][3]. Group 2 - The Fengzhou 220 kV project includes the construction of one substation and three main transformers, each with a capacity of 180 MVA [3]. - The commissioning of the Tengfei 220 kV substation allows for the successful connection of seven substations, completing the "last mile" of electricity delivery for several key substations [3]. - The project has seen improvements in both construction quality and progress through the integration of standardized construction and lean management practices [3]. - Following the commissioning, Hohhot plans to continue upgrading and optimizing the power grid structure, enhancing its intelligence and sustainability to support economic and social development [3].