Core Viewpoint - The company announced a delay in the completion of its large-scale intelligent production base for metal additive manufacturing, originally scheduled for December 2025, now postponed to June 2027 due to factors such as land supply and cultural relic exploration [1] Fundraising and Investment - In 2022, the company raised a net amount of 3.007 billion yuan through a private placement of shares, intended for the construction of the production base and other projects [1] - As of September 30, 2025, the cumulative investment in the project reached 783 million yuan, representing a progress rate of 31.99% [1] Board Decisions - On December 25, 2025, the company's board approved the extension of the fundraising project timeline and re-evaluation of the proposal, with no objections from the sponsor, CITIC Securities [1]
铂力特:金属增材制造生产基地募投项目延期至2027年6月