Core Viewpoint - The company announced a delay in the GEOVISOnline digital earth construction project, moving the completion date from December 2025 to June 2026 due to construction complexities related to super-tall buildings [1] Group 1: Project Details - The board of directors will meet on December 30, 2025, to review the proposal for the project delay [1] - The project was initially funded with 1.533 billion yuan in 2022, with a remaining balance of 213 million yuan as of the end of 2025 [1] - The delay is attributed to the unfinished acceptance of the research and development center [1] Group 2: Approval and Oversight - The matter does not require shareholder meeting approval, and the sponsoring institution has no objections [1]