历经13年 山西中部引黄工程西干线全线贯通
Xin Lang Cai Jing·2026-01-01 03:17

Core Viewpoint - The successful completion of the last segment of the Western Line of the Central Yellow River Diversion Project marks a significant milestone in a major water conservancy project that has taken 13 years, laying a solid foundation for the overall production and effectiveness of the project [1] Group 1: Project Overview - The Central Yellow River Diversion Project is located in the second vertical of the modern water network in Shanxi [1] - The planned annual water supply capacity of the project is 602 million cubic meters [1] - Upon completion, the project will add and improve irrigation areas by 1.5 million acres, fundamentally alleviating the water scarcity issues for industrial, agricultural, and ecological uses along the route [1] Group 2: Key Infrastructure - The Western Line serves as the core water conveyance channel of the Central Yellow River Diversion Project, with a total length of 107.22 kilometers, including a tunnel length of 93.38 kilometers [1]