云南锗业:“空间太阳能电池用锗晶片建设项目”完全建成后达到年产250万片锗晶片的产能
Mei Ri Jing Ji Xin Wen·2026-01-07 04:00

Core Viewpoint - The company is expanding its production capacity for germanium wafers, with a new project set to begin in March 2025, aiming for significant output increases by the end of 2025 [2] Group 1: Production Capacity - The company plans to implement a "germanium wafer construction project for space solar cells" starting in March 2025, with a construction period of 18 months [2] - By the end of 2025, the project aims to achieve an annual production capacity of 1.25 million germanium wafers, with a total capacity of 2.5 million wafers once fully completed [2] Group 2: Project Progress - The construction work for the aforementioned project is currently progressing as planned [2] - The company will disclose specific production and sales information regarding the related products in its annual report [2]