新天绿能:唐山LNG项目二阶段9#、10#、15#、16#储罐工程已完成机械完工验收
Zheng Quan Ri Bao·2026-01-09 13:40

Group 1 - The core viewpoint of the article highlights the progress of the Tangshan LNG project, specifically the completion of various engineering phases and the expected timeline for project completion by the end of 2025 [2] Group 2 - The second phase of the Tangshan LNG project has completed mechanical acceptance for storage tank engineering 9, 10, 15, and 16 [2] - The Wenhui water utilization project has completed its acceptance inspection [2] - Cumulatively, 46.7% of the first section of the process area for the second phase of the Tangshan LNG project has been completed [2] - The overall construction plan indicates that the second phase of the Tangshan LNG project is expected to be completed by the end of 2025 [2]