Vista Gold Sets Target for Start of Detailed Engineering and Design
Core Viewpoint - Vista Gold Corp. is making significant progress at its Mt Todd gold project, with plans to initiate detailed engineering and design by early 2027, leading to a 27-month design, construction, and commissioning process [1] Group 1: Project Development - The Mt Todd Feasibility Study, completed in July 2025, indicates the potential for near-term development of a smaller initial project by focusing on higher-priority areas [1]