Core Viewpoint - The company, Nongshang Environment, announced that its subsidiary, Xinsuan Shengyang, plans to invest 83.6963 million yuan in the construction of the Guangzhou Smart Innovation Valley computing power infrastructure project, but the project is facing delays due to funding issues [1] Group 1: Project Details - The initial expected construction period for the project was 3 months [1] - As of now, the funding progress has not met expectations, and all shareholders have not yet contributed their capital [1] - Although the company and its partners have continued to advance some preliminary work, the overall construction progress of the project has been stalled [1] Group 2: Future Outlook - If the necessary funding is not secured in a timely manner, the project may face further uncertainties [1] - The company will continue to urge and coordinate all parties involved to reach a consensus on funding solutions to get the project back on track [1]
农尚环境:控股子公司算力基础设施项目未能按原定计划推进