Group 1 - The company announced a delay in the "New Energy Vehicle Integrated Large Die Casting Project" to March 2027, originally scheduled for completion in March 2026 [1] - The extension is due to the downstream automotive customers' refined requirements regarding product specifications, technical compatibility, and delivery schedules, necessitating a longer construction period to enhance capacity utilization and investment returns [1] - The total amount of raised funds for the project is 400 million yuan, with a net amount of 392 million yuan fully deposited in a special account for raised funds [1] Group 2 - As of December 31, 2025, the cumulative investment in the project is 238 million yuan, representing an investment progress of 77.66% [1]
常青股份:新能源汽车一体化大型压铸项目延期至2027年3月