Hydro One Q4 Earnings Call Highlights
Yahoo Finance·2026-02-13 19:07

Barrie to Sudbury Transmission Line: Also designated after the quarter, Lebeter said this will be an approximately 290-kilometer, single-circuit, 500 kV line expected to be in service in 2032, with development work on a second single-circuit 500 kV line also to be carried out to support new generation opportunities in Northern Ontario.Greenstone Transmission Line (Northern Ontario): Designated after the quarter, this project is described as a 230-kilometer single-circuit line designed for future expansion, ...