CENTURY LITHIUM REPORTS UPDATED FEASIBILITY STUDY WITH AFTER-TAX NPV OF $4.01 BILLION AND OPERATING COSTS OF $4,389 PER TONNE OF LITHIUM CARBONATE FOR THE ANGEL ISLAND LITHIUM PROJECT, NEVADA
Prnewswire·2026-02-23 11:00

CENTURY LITHIUM REPORTS UPDATED FEASIBILITY STUDY WITH AFTER-TAX NPV OF $4.01 BILLION AND OPERATING COSTS OF $4,389 PER TONNE OF LITHIUM CARBONATE FOR THE ANGEL ISLAND LITHIUM PROJECT, NEVADA [Accessibility Statement] Skip NavigationFEASIBILITY STUDY HIGHLIGHTS- Initial Phase 1 throughput of 7,500 tonnes per day ("tpd"), expanding to 15,000 tpd in Year 5 (Phase 2)- Economic analysis based on a 40-year production schedule, with planned life-of-mine average production of approximately 26,500 tonnes per annum ...