扎波罗热核电站供电线路,已完成修复
中国能源报·2025-11-09 05:15
Group 1 - The external power supply line of the Zaporizhzhia Nuclear Power Plant, the Feodosia-Plavnaya-1 transmission line, has been repaired and reconnected to the grid, significantly enhancing the stability of the nuclear power plant's energy system [3] - The Feodosia-Plavnaya-1 transmission line had been out of service since May 7, while another external power line, Dniprovska, was interrupted due to ongoing artillery fire from Ukrainian forces for 30 days, but was restored and reconnected on October 23 [3] - The Director General of the International Atomic Energy Agency, Grossi, announced on November 7 that a localized ceasefire has begun in the vicinity of the Zaporizhzhia Nuclear Power Plant to facilitate necessary repair work [3]