Buenaventura(BVN) - 2022 Q4 - Earnings Call Presentation

Greenfield Projects – San Gabriel (Au) Feasibility - Optimized Plant Layout Project Maturity Highlights GEOLOGY MINE PLANT FACILITIES ENERGY WATER INFRA LAND PERMITS SAFETY WORKFORCE SOCIAL S FS D PFS • Engineering and procurement work offsite activities progressed as planned by a significant 64% and 83%, respectively, relative to total targeted for the project completion. • This thereby reduces overall project uncertainty and potentially enabling the recovery of a portion of time lost related to this proje ...