Warrior Met Coal(HCC) - 2024 Q4 - Earnings Call Presentation

February 13, 2025 Fourth Quarter and Full Year 2024 Results The revised project cost includes the original estimate of 700million,plusscopechangesof700 million, plus scope changes of 120-130million,plustheimpactofinflationarycostincreasesrangingfrom25to35percent.Therehavebeennochangestothetotalprojectcostestimaterangeof130 million, plus the impact of inflationary cost increases ranging from 25 to 35 percent. There have been no changes to the total project cost estimate range of 995 million to $1.075 billion. The estimated NPV, estimated IRR, estimated Payback calculation, projected valuation amounts, estimated production potential, anticipated schedule, estimated ...