IREN (NasdaqGS:IREN)  Earnings Call Presentation
Contract Overview - IREN secured a $9.7 billion AI cloud contract [1,9,14] - The contract includes $5.8 billion in GPU capex, including ancillaries [14] - The contract term is 5 years, with phased starts targeted in 2026 [9,14] - A 20% prepayment is included, credited to years 3-5 [9,14] Financial Projections - The estimated project EBITDA margin is approximately 85% [11] - The annualized run-rate revenue (ARR) is $1.94 billion [11] - The company projects $2.5 billion ARR, including other customers [25] Data Center Infrastructure - IREN is building 200MW of data centers for AI cloud services [9,16] - The estimated all-in capex is $14-16 million per MW (IT load) [19] - The company has 750MW of available power in Childress, Texas [20,22]