Company Operations - SMGP's fifth unit officially commenced commercial operation on December 28, 2024, at 00:00 local time (01:00 Beijing time) with a net power generation capacity of 31.34 MW [1] - SMGP successfully completed the 72-hour rated capacity test (URC) for the fifth unit between December 12 and 15, 2024 [1] Industry Developments - The commercial operation of SMGP's fifth unit is based on the power purchase agreement with Indonesia's state-owned electricity company, PLN, and the URC report signed by PLN headquarters [1]