华峰化学股份有限公司 关于热电联产扩建项目调整的公告

Group 1 - The company has decided to adjust the expansion project of the cogeneration project, which was approved in the 11th meeting of the 9th Board of Directors held on June 25, 2025 [2][4] - The original total investment for the project was planned at 510 million yuan, with a scale of 2 boilers and 2 turbines, but only 1 boiler and 1 turbine have been completed and are currently operational [3] - The decision to halt further investment is based on market research and the current demand for steam, ensuring that the existing capacity meets the needs of surrounding enterprises [3][4] Group 2 - The adjustment of the project aims to enhance economic efficiency and avoid resource waste, aligning with the current market environment and the company's operational situation [4] - The project is expected to support the steam demand of the surrounding enterprises, improve energy utilization, promote energy conservation and emission reduction, and contribute positively to regional economic development [4]