“三修”计划总投资达10.2亿元 沈阳供热企业“冬病夏治”正当时
Ren Min Wang·2025-06-27 06:48

Group 1 - The total investment for Shenyang's heating "three repairs" project this year is 1.02 billion yuan, covering key areas such as pipeline renovation, equipment maintenance, and coal storage [1] - The project aims to replace over 10,000 meters of old pipelines, with 3,200 meters of unit pipelines involved, and is expected to be completed by the end of July [2] - The heating system repair progress includes the renovation of 300 heating boilers, with 149 completed, and 200 kilometers of heating pipelines, with 68.1 kilometers completed [3] Group 2 - The coal storage for the upcoming winter is projected at 6.3 million tons, with 2.52 million tons already stored, achieving a storage rate of 40% [3] - The company has invested 18 million yuan in "three repairs" work, with 75% completed and expected to finish by late August [2] - The company is implementing targeted solutions for users with specific heating issues, ensuring effective communication and adjustments as needed [2]