新奥舟山LNG接收站三期项目投运,年接卸能力有望达1000万吨
Core Viewpoint - The Zhoushan LNG receiving station's Phase III project has been completed and put into operation ahead of schedule, significantly enhancing gas supply capabilities for the Yangtze River Delta region [1] Group 1: Project Completion - The Phase III project of the Zhoushan LNG receiving station officially commenced operations on August 6, 2025, with the first LNG ship unloading into tank 7 [1] - The project was completed in 29 months, which is 4 months ahead of the planned schedule [1] Group 2: Capacity and Demand - The annual unloading capacity of the new facilities is expected to reach 10 million tons [1] - The project will meet the annual gas demand for over 30 million households in the Yangtze River Delta region [1]