Core Viewpoint - China Nuclear Power Co., Ltd. has successfully poured the first batch of concrete for the nuclear island of Unit 1 at the Zhejiang Jin Qimen Nuclear Power Plant, marking a significant milestone in its construction [1]. Group 1: Project Details - The first concrete pour (FCD) for Unit 1 of the Zhejiang Jin Qimen Nuclear Power Plant took place on August 10, 2025 [1]. - The plant utilizes China's independently developed "Hualong One" nuclear technology, with a single unit rated capacity of 1.215 million kilowatts [1]. - The design operational lifespan of the unit is 60 years [1]. Group 2: Company Capacity - Following the FCD, the number of nuclear power units under construction controlled by the company will reach 13, with a total installed capacity of 15.138 million kilowatts [1].
中国核电: 中国核电关于浙江金七门核电站1号机组浇筑核岛第一罐混凝土的公告