北新路桥:中标3.99亿元项目

Core Points - The company has been awarded a construction project for the G687 road segment in Xinjiang, with a bid amount of ¥398,724,320.00 [1] - The project duration is set for 944 calendar days, with a quality standard of "qualified" [1] - The project involves constructing a 95.531 km long road, adhering to a dual-lane secondary road standard, with a design speed of 80 km/h [1] Financial Impact - Winning this bid is expected to enhance the company's market competitiveness and market share [1] - Successful implementation of the project is anticipated to have a positive impact on the company's future performance [1] Project Specifications - The road will include one medium bridge and a total of 67 culverts, consisting of 65 covered culverts and 2 open culverts [1] - Additional features include one at-grade intersection, 56 road openings, 20 pipeline crossings, and 10 emergency stopping areas [1]