江苏神通:公司2024年新签核电阀门订单大多将自2026年起陆续交付
Core Viewpoint - Jiangsu Shentong (002438) announced that the delivery cycle for new nuclear power valve projects is typically 2-3 years, which will affect the timing of new orders and deliveries [1] Group 1: Company Operations - The majority of new nuclear valve orders signed in 2024 will be delivered starting in 2026 [1] - The nuclear valves delivered in 2025 will primarily come from orders placed in 2022 and 2023 [1] - Current deliveries are proceeding normally, and the revenue from the nuclear valve business is expected to maintain steady growth this year [1]