快车道实现临时通车,坝河桥预计明年6月全面竣工
Xin Jing Bao·2025-11-12 02:19
Core Viewpoint - The construction of the Bahe Bridge in the Dongba North area of Chaoyang District is progressing well, with completion expected by June next year [1] Construction Progress - The lower structure of the east side of the bridge is 90% complete, while the installation of the steel arch structure on the west side is ongoing [1] - The west side's fast lane has been completed and is temporarily open for traffic, featuring a width of 14 meters, which is an expansion compared to the old bridge [1] Traffic Management - The temporary traffic setup includes two-way lanes, along with comprehensive traffic signage, signal lights, and protective facilities to ensure safe passage [1]