和邦生物:烟峰磷矿设计产能100万吨/年

Core Viewpoint - The company plans to enhance its logistics control to reduce costs associated with its Wonarah phosphate mine, which is expected to commence production in 2026 [2] Group 1: Production Capacity - The designed production capacity for the Yingfeng phosphate mine is 1 million tons per year [2] - The designed production capacity for the Liujiashan phosphate mine is 1.2 million tons per year [2] - The first phase of the Wonarah phosphate mine is designed for a production capacity of 700,000 tons per year [2] Group 2: Project Development - The Wonarah phosphate mine is an open-pit mine, and its construction progress is expected to be relatively fast [2] - The company is implementing a logistics full-chain control plan to lower logistics costs, which are the largest cost component for the mine [2] Group 3: Future Plans - The company aims to achieve phosphate ore mining and sales at the Wonarah mine by 2026 [2]