Workflow
中煤榆林煤炭深加工基地项目大件设备吊装圆满收官

Core Viewpoint - The successful completion of the lifting of four key pieces of equipment marks a significant milestone in the construction of the coal deep processing project in Yulin, undertaken by Sinopec's Fourth Construction Company [1] Group 1: Project Progress - The lifting of the last four critical devices (E-2701A/B and E-2614A/B) has been completed safely and smoothly, concluding the lifting tasks for the olefin separation unit [1] - The project has achieved its engineering control points on schedule, thanks to the optimization of construction plans and continuous improvement of construction methods [1] Group 2: Team Efforts - The successful completion of the lifting tasks is attributed to the collective efforts of all participating employees, laying a solid foundation for subsequent work such as the installation of process pipelines [1] - The project team is fully engaged and motivated, making steady progress towards the project's defined goals in the next construction phase [1]