Group 1 - The company plans to invest in the construction of a 700,000 kW onshore wind power project in Caofeidian, which includes a 350,000 kW guaranteed project and a 350,000 kW market-oriented subproject, as well as a 250,000 kW wind power project in Tangshan Fengnan [1] - The total planned capacity for the three projects is 950,000 kW, with a total investment not exceeding RMB 4.38 billion; the company's equity contribution will be 20%, amounting to no more than RMB 876 million, funded by its own resources, while the remaining funds will be sourced through loans from financial institutions [1] - The construction period for the Caofeidian guaranteed and market-oriented projects is expected to be 12 months, while the Fengnan project is anticipated to take 18 months, with an operational period of 20 years post-completion [1]
大金重工(002487.SZ)拟投建多个风电项目 总投资不超43.8亿元